Monday, May 16, 2011

Fluid Cooler












Another quick turn around on a fluid cooler. As usual we keep the down time to 24 hours. From Friday at 5:00 PM to Saturday at 5:00 PM. This project was estimated, sold and project managed to success by Mike Peet. The crew was close to same as the last tower in the fall. One pipefitter to coordinate the piping changes from the existing EVAPCO to the replacement RECOLD. One service technician to install the trim, controls, and VFD on the new tower. One electrician to reconfigure the power supply and a utility technician to assist as needed. Once again attention to detail, strategic planning and a team effort paid off. The pictures really tell the story and for this one we went from train car to full operation in a week.